Mighty Shipping
Knowledge Base · Export Process

Export Cut-off Times Explained: CY Open, CY Cut-off, Customs, SI and VGM

Your booking confirmation lists a row of dates — CY open, CY cut-off, customs cut-off, SI cut-off, VGM cut-off. Which comes first, and which one gets your container rolled if you miss it? One table, one timeline, and a simple way to plan backwards from the sailing date.

Updated 2026-11-18 ~8 min read Mighty ops team

An FCL export has to clear several deadlines: you can gate in only after CY open, the full box must be at the terminal before the CY cut-off, customs must release it before the customs cut-off, the carrier needs your shipping instructions (SI) before the SI cut-off, and the VGM must be filed before the VGM cut-off. The box only gets loaded when all four are in place: at the port, released, SI filed and VGM filed. Miss one and it can be rolled. The booking confirmation and terminal notice always govern, but the usual pattern is: CY open 5–7 days before departure, CY and customs cut-off 1–2 days before, SI and VGM at the same time as or earlier than the CY cut-off — and on US, EU and Japan trades, SI cut-off comes another 1–2 days earlier because of advance manifest rules. The safest approach is to anchor on the CY cut-off, plan backwards, and keep half a day to a day of buffer at every step.

1. All Export Cut-offs in One Table

Listed roughly in order. The "typical timing" column reflects common industry practice only — for every shipment, follow the carrier's booking confirmation (S/O) and the terminal's gate-in notice.

Milestone Also called What it controls Typical timing (vs. ETD) If you miss it
CY open Earliest receiving date (ERD) Terminal starts accepting full boxes for this sailing 5–7 days before ETD Too early to gate in — apply for early gate-in or wait at an off-terminal depot
SI cut-off Documentation cut-off, B/L instructions B/L data submitted to the carrier 2–3 days before ETD; often 1–2 days earlier on US, EU and Japan trades Late SI fee, paid B/L amendments; on advance-manifest trades, possibly not loaded
VGM cut-off Weight cut-off Verified gross mass of the container Same as or slightly before SI cut-off; never after CY cut-off No VGM, no loading
Manifest cut-off AMS / ACI / ENS / AFR cut-off Manifest sent to destination customs US, Canada, EU etc.: at least 24 hours before loading Destination customs may issue a do-not-load order; penalties possible
CY cut-off Port cut-off, cargo cut-off Full box must be inside the terminal 1–2 days before ETD Terminal refuses the box — request late gate-in or roll to next sailing
Customs cut-off Release cut-off Customs release must reach the terminal Same time as, or a few hours after, CY cut-off Not released, not planned — shut out or rolled
Departure ETD Vessel sails — —

Easy way to remember: CY open = "the gate opens", CY cut-off = "box is in", customs cut-off = "customs says yes", SI cut-off = "paperwork is in", VGM = "weight is declared". Forwarders in China sum it up as: paperwork before cargo, cargo before CY cut-off, release before sailing.

2. What Each Cut-off Actually Means

2.1 CY open: the terminal starts taking your boxes

Terminal yards allocate space by sailing. Once the schedule is fixed, the terminal publishes when it will start receiving full containers for that voyage — usually 5–7 days before departure. Arrive earlier and the terminal will normally turn you away; you either apply for early gate-in (often charged) or park the full box at an off-terminal depot until CY open.

  • When the factory loads too early and CY open is late, you end up with a packed container and nowhere to put it. Check CY open before fixing the stuffing date.
  • If the vessel is delayed, CY open shifts too. Reconfirm with your forwarder the day before stuffing.

2.2 CY cut-off: last time to get the full box into the terminal

After the CY cut-off, the terminal stops receiving full containers for the sailing because it starts the stowage plan — deciding where each box sits on the ship. This is the hardest deadline of the whole shipment.

  • Gate queues peak on cut-off day; waits of several hours are normal. Aim to have the box in the terminal at least 24 hours before the CY cut-off.
  • Allow for driving time, gate queues and weather (in Qingdao, winter gales and summer typhoons both cause delays).

2.3 Customs cut-off: last time for the export release

At Chinese ports, "customs cut-off" usually means the release cut-off: the export declaration must be cleared by customs and the release message must reach the terminal before this time, or the box will not be planned onto the vessel. It typically falls on the same day as the CY cut-off, a few hours later.

  • A formal declaration normally needs the box to be at the port with an arrival report first — another reason to gate in early.
  • If customs selects the box for inspection, release can take an extra half day to several days. File the declaration 1–2 working days before the customs cut-off. See our export customs declaration guide.
  • People use "cut-off" loosely — some mean CY cut-off, some mean SI cut-off. Always write the milestone name and the exact time together.

2.4 SI cut-off: last time to send B/L data to the carrier

SI cut-off is the carrier's deadline for shipping instructions: shipper, consignee, notify party, description of goods, packages, gross weight, volume, marks, container and seal numbers. The carrier uses the SI to:

  • issue the bill of lading (see bill of lading types for release options);
  • file the manifest with destination customs.

A late SI usually triggers a late SI fee. Changing B/L details after the cut-off means an amendment fee, and changes after the destination manifest has been filed cost more and carry more risk.

2.5 VGM cut-off: last time to declare the container weight

Under the IMO's SOLAS convention, every packed export container needs a verified gross mass (VGM) — cargo, packaging, pallets and container tare combined — before loading. No VGM, no loading. The shipper is responsible and can either weigh the packed container (Method 1) or weigh all contents and add the tare (Method 2).

  • The carrier sets the VGM cut-off; it is commonly the same as or slightly earlier than the SI cut-off, and never later than the CY cut-off.
  • If the VGM and B/L gross weight differ a lot, the carrier may ask for a correction or charge a fee. See container sizes and VGM.

2.6 Manifest cut-off: why US-bound SI deadlines are earlier

The US, Canada, the EU and Japan require the manifest to reach their customs before the cargo is loaded in China. US AMS, for example, must be filed at least 24 hours before loading, and EU ICS2 also requires advance filing. Carriers and forwarders need time to file, so SI cut-offs on these trades are usually 1–2 days earlier than on other routes. Details: export booking process: AMS/ENS/AFR.

3. Sample Timeline: Sailing on Friday

A standard dry FCL shipment departing Friday (indicative only; follow the actual carrier and terminal notices):

When Milestone What to do
By the previous Friday Booking confirmed Copy every cut-off from the booking confirmation; book trucking; prepare customs documents
Sunday / Monday CY open Pick up the empty, stuff at the factory
Tuesday Gate in Declare to customs as soon as the box is in; on advance-manifest trades (e.g. US), submit SI today
Wednesday SI and VGM cut-off (standard trades) Submit SI and VGM, check the draft B/L
Thursday morning CY cut-off Box must be in the terminal (ideally since Wednesday)
Thursday afternoon Customs cut-off Customs release must reach the terminal
Friday Departure Confirm loading, follow up on B/L issuance

For Qingdao terminal cut-off patterns, trucking and common delays, see Qingdao Port export operations.

4. Plan Backwards from the CY Cut-off

The most common factory question is "when should we stuff?" The answer: fix the CY cut-off first, then work backwards.

  1. Gate-in = at least 24 hours before CY cut-off. Add half a day in peak season or before holidays.
  2. Stuffing date = gate-in minus trucking and loading time. Local factories usually stuff the day before; inland factories need to add the long-haul drive.
  3. Empty pick-up = stuffing day or the day before, but not so far ahead of CY open that the full box has nowhere to go.
  4. Customs documents = ready before stuffing. Declare the moment the box gates in and leave room for inspection.
  5. SI and VGM = prepare right after booking; submit as soon as you have container/seal numbers and the weight. Don't wait for the last hour.

Factory loading vs. port CFS stuffing: if cargo is delivered to a port-area warehouse for stuffing, the warehouse has its own cargo receiving cut-off, usually 1–2 days before the CY cut-off. LCL works the same way with the CFS cut-off. See factory loading vs. port CFS stuffing and the LCL export guide.

5. Missed a Cut-off? What You Can Do

Missed Possible fix Likely costs
CY cut-off Have your forwarder request a late gate-in from carrier and terminal right away; otherwise roll to the next sailing Late gate fee, rebooking fee, storage
Customs cut-off Request late release (depends on vessel planning); if not possible, roll or shut out and withdraw the box Rebooking, amendment and shut-out related fees
SI cut-off Submit the SI immediately — usually still loaded, but charged; on US-type trades the manifest may miss its window Late SI fee, amendment fee
VGM Submit immediately; there is a chance if final stowage isn't done Possible fee, or the box is left behind
  • Late gate-in is never guaranteed. When the vessel is full or planning has started, it's almost always refused. Don't treat it as a plan.
  • Even if you meet every cut-off, the carrier may roll your box because of overbooking. See the ocean shipping exceptions SOP.

6. When Cut-offs Come Earlier

  • Dangerous goods: DG declaration and terminal approval come first, so SI and CY cut-offs are often 1–3 days earlier than for general cargo. See chemical products ocean export.
  • Reefers and special equipment: reefers need plug slots, open tops and flat racks need special handling — cut-offs are earlier. See the reefer export guide and OOG container guide.
  • Before holidays: before China's National Day and Chinese New Year, customs, terminals and trucks are stretched and carriers often bring cut-offs forward. Confirm a week ahead.
  • Schedule changes: if the vessel arrives early, the CY cut-off moves earlier; if it's late, it may slip. Check the schedule daily, not just at booking.

7. Pre-shipment Checklist

  • □ CY open, SI, VGM, CY and customs cut-offs from the booking confirmation are all in the shipping calendar
  • □ Confirmed whether the trade needs advance manifest filing (US, Canada, EU, Japan…) and an earlier SI cut-off
  • □ Stuffing date planned backwards from "in the terminal 24 hours before CY cut-off", and not too far ahead of CY open
  • □ Trucking booked with buffer for queues and weather
  • □ Customs documents (invoice, packing list, declaration elements, licences) ready before stuffing
  • □ SI details (parties, description, packages, weight, volume, marks) agreed with the buyer; submitted once container and seal numbers are known
  • □ VGM method decided; weight matches the B/L gross weight
  • □ Earlier cut-offs confirmed separately for DG, reefer, special equipment, or pre-holiday sailings

8. How Mighty Shipping Can Help

  • Cut-off schedule: after booking, we send you and the factory one timeline with every milestone, and alert you immediately if the schedule changes.
  • Trucking + customs in one team: our trucking and brokerage teams work together so declarations go in as soon as the box gates in.
  • SI and VGM handling: we check B/L data, arrange weighing and file the VGM for you.
  • Late gate and rebooking: if something slips, we work with the carrier and terminal on late gate-in or the next best sailing straight away.

Not sure how to schedule this shipment?

Send us the origin, destination, cargo, container type and target ship date. Our ops team will reply with sailing options, every cut-off and a recommended stuffing date.

Get in touch

FAQ

What is the difference between CY cut-off and customs cut-off?

CY cut-off is the last time the full box can enter the terminal — is it physically there? Customs cut-off (release cut-off) is the last time the customs release can reach the terminal — has the declaration cleared? Usually the same day, customs a few hours later. You need both to be loaded.

What happens if I miss the SI cut-off?

Usually a late SI fee, plus paid amendments to the B/L afterwards. On trades with advance manifest rules (US, Canada, EU, Japan), a late SI can stop the box from being loaded.

When is the VGM cut-off, and what if I don't submit it?

Check the booking confirmation; it's usually the same as or slightly before the SI cut-off and never after the CY cut-off. Under SOLAS, a container without a VGM must not be loaded.

What does CY open mean? Can I gate in before it?

It's when the terminal starts receiving full boxes for the sailing, commonly 5–7 days before departure. Before that you need early gate-in approval (often charged) or an off-terminal depot.

If I miss the CY or customs cut-off, can I still make the vessel?

You can request a late gate-in or late release. Approval depends on vessel planning and terminal workload, is usually charged, and is rare in peak season. Otherwise the box rolls to the next sailing.

References and Further Reading

Sources accessed 2026-11-18. The "typical timing" figures in this guide reflect common industry practice, not fixed rules; every shipment follows the carrier's booking confirmation and the terminal's notice.

Disclaimer: This is a general guide to ocean export cut-off times. Cut-offs differ by carrier, terminal, trade and voyage and change with the schedule; the booking confirmation, terminal notices and your forwarder's written instructions always govern.